Continuing where I left off with my Foundation post, we had more work to do with concrete. We had a few foundation walls, and our entryway that needed to be completed. Since our property was on a North/South slope, we have a 6 ft wall on the southern side of the lot, and a smaller 4 ft wall on the northern side between the driveway and city’s sewer easement.
Back in April 2018 they started to build out the forms for the footings, for the walls and entryway. They moved pretty quickly and they poured the concrete in early May. I remember, for some silly reason, that it seemed early for them to be doing this work already. I am not quite sure why I felt this way, but I just thought that there was a lot of work to be done on the interior of the house, and it seemed like focusing on the house itself was a higher priority. At the time, in April, the house was mostly a skeleton with clothes on; All of the interior walls were open and we had most of the siding completed. We were waiting for the plumbers and electricians to finish their rough-ins so that we could move on to the next phase and finally work on the finishes.
At the end of July we began talking to our stone guy, Vitaly, who said that he would be finishing up his current job at the end of August, and would be available to start working on the stone for the front of our house after July 4th. We didn’t originally want stone on the walls around the house, but damage from one of Joe’s workers, Javier, caused us to have to cover the concrete with something.
Back when our foundation was poured, they had to remove the snap cones (nails basically) from the outside of the house so that they could apply the dimple-mat and waterproof the foundation. Javier didn’t seem to know that these snap-cones were meant to be twisted off and ended up using a Sawzall to cut them, damaging the wall, and making it impossible to remove the piece of metal inside. Typically the snap-cones have a weak spot deep within the hole, and when you twist them off, they leave a really nice and clean hole, as seen below.
So since we had to hide the damage with some sort of veneer, we decided that we’d continue the stone from the house and cover all of these walls in the front of the house with the same stone. The image to the right was something I drew up when I was trying to figure out how much stone to order for the initial stone setting. I knew we would end up needing more for the entryway, but this bare minimum should cover what was needed till the stairs were poured and completed.
Vitaly ended up taking a bit longer than planned to start working on our job and showed up towards the latter half of July. I remember it being extremely hot around this time since I was on paternity leave and I had to find a cool places to feed Matilda. I also remember Vitaly suffering in the heat. He spent a lot of his day sitting in his truck with the A/C on, smoking constantly, and took a very very long time to get much done. It was understandable since it was very very hot, but I could tell that he really didn’t want to be there.
There were many excuses over the course of the summer why he wasn’t available to come back and finish the job. Initially he said that it was too hot to work outside, which was understandable, and then he ended up taking another job that was paying him double, which also was understandable since I wasn’t paying him double, and then there was a game where he would tell me a date that he’d be there only to miss it. He did finally show up again to finish things, but that happened to be on the day that they were delivering the drywall and he understandably didn’t want to be working under tons material moved overhead. After all of this, it finally came down to him (and Joe) wanting to wait for the rest of the concrete to be poured so that he could do everything in one go.
So after the long-winded story about how difficult it had been to get Vitaly to install the stone, we were basically waiting for Lamb Concrete again to finish building and pouring those foundation walls. Every time I asked them directly, or through Joe, we kept getting told that it would be about a week or two out, and this kept going back and forth for most of the summer. They did finally showed up again in September, almost 4 months after those footings were poured to continue building the walls. Unfortunately the weather had changed a bit and we had water issues to deal with now.
Weather did eventually clear up and they were able to finish the walls, however, we did hit another snag. When they finally poured the concrete on September 26th, one of the form walls busted, splitting the 1-1/8″ plywood clean down the middle, spewing mud everywhere. Half of the wall had collapsed and they were scrambling to get the wet concrete away from the house and the foundation.
The lead guy, Steve, who had been in the concrete business for over 30 years, said that he had never seen something like this happen before. He had never seen one of those plywood forms bust and commented how the forms they use are the best ones money can buy, and lamented how some of the forms they were using had lasted over 20 years. The forms they used for this particular wall were basically brand new, acquired recently because of how much extra work they were having, and they had used it for this particular wall because I had asked to have this be a “show wall” with an Architectural finish, and I basically wanted it to look nice without having to spend more money by covering it with stone or stucco.
The bad luck with the wall collapsing was frustrating, but I can’t really blame anybody for that happening and they did a mostly-good job at fixing the situation; It was just bad luck. It was very annoying having to wait almost a month again for them to pour the rest of that wall. It wasn’t completed till about a week ago on November 1st.
So here we are in the month of November and are still waiting to backfill, still waiting for utilities to be hooked up, still waiting for Vitaly to finish the stone on the garage and those walls. I can’t believe I thought starting this in April seemed early, I was so very wrong. The interior of the house is actually moving along really nicely at this point in time, and I actually wouldn’t be surprised to see that done by the end of the year, or January sometime at the latest. The rest of this exterior stuff is really holding things up now and think that it’s likely to extend well in to spring next year.
I really hope that I don’t have more stories to share with concrete, since we do have a few more things to do: Those stairs and the driveway. Wish us luck!